Library Building Update Series (Week of June 21, 2019)
Details
Published
Shelving, flooring, ceiling beams...and more books!
The shelving for the Quaker & Special Collections vault is completed and shelving for Level 2 is underway. Stone flooring at the Level 2 ramp entrance has been laid; ceiling beams for the Philips Wing are being installed. Books are still being moved to the stacks on Level 0 and we'll begin moving Quaker & Special Collections this week.