Library Building Project Update Series (Week of March 1, 2019)
Details
Published
Work continues both inside and outside, including skylights and the elevator.
Stone veneer work is underway with brickwork to commence next week. Glass skylights are installed. Painting on Level 1 is underway. Drywall framing on Level 2 is targeted for this and next week. Limestone columns were cleaned. The elevator is being installed; the car is being built. Work continues on fire protection and sprinkler system for Level 2.