Details
Ceiling grids are being installed on Level 0 and more framing of walls on Level 2 is progressing. Level 0 walls are primed and painting will continue in the coming days. Network wiring has begun. Color choices for Level 0 and Level 1 were selected and approved.
Read more about the project on the Library Renovation website.
Ceiling grids are being installed on Level 0 and more framing of walls on Level 2 is progressing. Level 0 walls are primed and painting will continue in the coming days. Network wiring has begun. Color choices for Level 0 and Level 1 were selected and approved.
Magill Library closed at the end of the Fall 2017 semester and will reopen as the Lutnick Library when the construction is completed. Read more about the project on the Library Renovation website.