Library Building Project Update Series (Weeks of January 18 and January 25, 2019)
Details
Published
Painting of Level 0 is complete; framing for clerestory and South Curtain walls installed. Network wiring continues on Levels 1 and 2. Ductwork and and chilled beam installation moving forward. Level 1 internal walls complete.
Read more about the project on the Library Renovation website.
Painting of Level 0 is complete; framing for clerestory and South Curtain walls installed. Network wiring continues on Levels 1 and 2. Ductwork and and chilled beam installation moving forward. Level 1 internal walls complete.
Magill Library closed at the end of the Fall 2017 semester and will reopen as the Lutnick Library when the construction is completed. Read more about the project on the Library Renovation website.