Library Building Project Update Series (Week of September 7, 2018)
Details
Published
Exterior foundation walls were poured, shelving pre-planning is complete, and finishing and furniture discussions are underway.
Read more about the project on the Library Renovation website.
Exterior foundation walls were poured and the Tier 1 slab on grade will be poured next week with Tier 2 form work on its way shortly thereafter. The shelving pre-planning is complete and material will soon be ordered. Finishing and furniture discussions are underway with plans to use some of our campus wood for some of the tables and benches.
Magill Library closed at the end of the Fall 2017 semester and will reopen as the Lutnick Library when the construction is completed. Read more about the project on the Library Renovation website.